Town of Berryville
Wastewater Treatment Plant Upgrade Report

Town of Berryville
Wastewater Treatment Plant
Upgrade Report October 6 2009

The Town is close to placing the Wastewater Treatment Project out for construction bids. Designs are completed and ready for printing. We are waiting final approval from DEQ and the project will be released. A copy of the general site layout is available on this site for review. The system includes a new Membrane Biological Reactor with a design flow of 0.7 MGD capable of meeting a nutrient discharge of 4.0 mg/l total nitrogen and 0.3 mg/l total phosphorus. The system includes new head works facility, biological treatment process, operations building and laboratory, and improvements to the current ultraviolet disinfection and effluent pumping systems. A biosolids dewatering facility is also being added.

A public hearing for the purpose of receiving comments on the Environmental Assessment for this project will be held on November 10, 2009 at the Berryville / Clarke County Government Center at 7:30 pm. A copy is available for review at the Town office Monday through Friday between the hours of 9:00 am and 4:00 pm. Written comments should be directed to David Tyrrell, Director of Utilities 101 Chalmers Court, Suite A, Berryville VA 22611and should be post marked by November 10, 2009.

Tentative Project Schedule
(Schedules are subject to change)

Activity                                              Start Date     End Date      Comments

 

Notice to Proceed                                                    10/6/2006    Completed

 

Establish Growth Projections        10/24/2006    12/26/2006    Completed

 

Preliminary Process

Alternative Screening                     10/9/2006        2/26/2007    Completed

 

Review Workshop

with Town Staff                                                        3/26/2007    Completed

 

Submit Draft PER to

Town of Berryville for review                                 7/30/2007    Completed

 

Submit PER to DEQ for review                               9/15/2007    Completed

 

Final Design                                     12/14/2007     7/30/2009     Completed

 

DEQ Review Period                            8/1/2009      10/5/2009     Under DEQ review

 

Bidding for Construction                   10/5/2009      Waiting for Final DEQ approval to release

 

Construction contract Award         11/30/2009

 

Construction Phase                        11/30/2009       4/16/2012

 

Startup and Operational                 11/28/2011    System to be operational and letter of substantial completion delivered to DEQ on or before this date.