The Town is close to placing the Wastewater Treatment Project out for construction bids. Designs are completed and ready for printing. We are waiting final approval from DEQ and the project will be released. A copy of the general site layout is available on this site for review. The system includes a new Membrane Biological Reactor with a design flow of 0.7 MGD capable of meeting a nutrient discharge of 4.0 mg/l total nitrogen and 0.3 mg/l total phosphorus. The system includes new head works facility, biological treatment process, operations building and laboratory, and improvements to the current ultraviolet disinfection and effluent pumping systems. A biosolids dewatering facility is also being added.
A public hearing for the purpose of receiving comments on the Environmental Assessment for this project will be held on November 10, 2009 at the Berryville / Clarke County Government Center at 7:30 pm. A copy is available for review at the Town office Monday through Friday between the hours of 9:00 am and 4:00 pm. Written comments should be directed to David Tyrrell, Director of Utilities 101 Chalmers Court, Suite A, Berryville VA 22611and should be post marked by November 10, 2009.
Tentative Project Schedule
(Schedules are subject to change)
Activity Start Date End Date Comments
Notice to Proceed 10/6/2006 Completed
Establish Growth Projections 10/24/2006 12/26/2006 Completed
Preliminary Process
Alternative Screening 10/9/2006 2/26/2007 Completed
Review Workshop
with Town Staff 3/26/2007 Completed
Submit Draft PER to
Town of Berryville for review 7/30/2007 Completed
Submit PER to DEQ for review 9/15/2007 Completed
Final Design 12/14/2007 7/30/2009 Completed
DEQ Review Period 8/1/2009 10/5/2009 Under DEQ review
Bidding for Construction 10/5/2009 Waiting for Final DEQ approval to release
Construction contract Award 11/30/2009
Construction Phase 11/30/2009 4/16/2012
Startup and Operational 11/28/2011 System to be operational and letter of substantial completion delivered to DEQ on or before this date.